Page 1 of 1
4/8/14 Track Work
Posted:
Tue Apr 08, 2014 12:34 pm
by Larry Gibson
Section crew started to construct a second track panel this afternoon.
Re: 4/8/14 Track Work
Posted:
Tue Apr 08, 2014 4:59 pm
by Larry Gibson
Second Panel completed.
Re: 4/8/14 Track Work
Posted:
Thu Apr 10, 2014 2:51 pm
by Allan Kirkpatrick
curiouser and curiouser!! Are there 15 or 18 track panels constructed now?
Does anyone know where they are going to be used?
Re: 4/8/14 Track Work
Posted:
Thu Apr 10, 2014 3:49 pm
by Tom Casper
Yes, Mr. Bush said "They will be used to relay the track between the Shop and the ash pit."
John Bush