Cumbres Pass week 3 roof going up

Unread postPosted: Wed Jul 22, 2020 9:36 am
by Sharon Evans
This week is being devoted to getting the roof on the car inspector's house. A slight glitch was experienced when the crane that was to lift the large center sill beam up somehow did not happen. Not to worry since the intrepid Friends crew went ahead and got the monster up themselves the old fashion way. Thanks to Tom Simco and John Cole for these pictures.
Working to get the center beam support straight.jpg
Working to get the center beam support straight

Ridge Beam Set.jpg
The level is on the support beam to ensure it is plumb
Ridge Beam Set.jpg (321.71 KiB) Viewed 3542 times

Ridge Beam Set2.jpg
Showing the work ongoing with scaffolding being used to help support the center beam

Looking at the center sill beam in place.jpg
Looking at the center sill beam in place
Looking at the center sill beam in place.jpg (97.57 KiB) Viewed 3542 times

Steading the wood as its lifted.jpg
Steading the wood as its lifted.jpg (95.72 KiB) Viewed 3542 times

First Rafters in place (1).jpg
First Rafters in place (1).jpg (285.04 KiB) Viewed 3542 times

Ridge Beam Set3.jpg
Overall view of the car inspector's house with the roof work progressing
Ridge Beam Set3.jpg (252.26 KiB) Viewed 3542 times


.

Re: Cumbres Pass week 3 roof going up

Unread postPosted: Wed Jul 22, 2020 10:55 am
by Craig Kumler
Looking really good!

Re: Cumbres Pass week 3 roof going up

Unread postPosted: Sat Jul 25, 2020 2:22 pm
by Sharon Evans
More pictures of the second floor and roof being built.
c The first floor is being framed out (1 of 1).jpg
The first floor is being framed out

zc Another angle of the framing on the ground floor.jpg
Another angle of the framing on the ground floor

c Measuring out the cut for a board at Cumbres (1 of 1).jpg
Measuring out the cut for a board at Cumbres

c working on the siding at the Car Inspectors house at Cumbres (1 of 1).jpg
working on the siding at the Car Inspectors house at Cumbres

c View of the fig used to get to and attach the rafters to the center beam  (1 of 1).jpg
View of the rig used to get to and attach the rafters to the center beam

c A long shot of the work on the center beam (1 of 1).jpg
A long shot of the work on the center beam

c The high tech method of getting the boards up to the second level of the house (1 of 1).jpg
The high tech method of getting the boards up to the second level of the house

c The rafter is now being positioned so it can be attached (1 of 1).jpg
The rafter is now being positioned so it can be attached

c In place and now will be attacted (1 of 1).jpg
Sometimes you have to use a bit of force to get it to fit

c A rafter is pulled up  (1 of 1).jpg
A rafter is pulled up

c In place and now will be attacted (1 of 1).jpg
In place and now will be attracted

c Attaching a rafter to the center beam of the house (1 of 1).jpg
Attaching a rafter to the center beam of the house

c Another shot of getting the rafter boards up to the second level (1 of 1).jpg
Another shot of getting the rafter boards up to the second level

c The roof rafters arae now in place ready for the actual roof to be installed (1 of 1).jpg
The roof rafters are now in place ready for the actual roof to be installed

c Looking down the second level from an end (1 of 1).jpg
Looking down the second level from an end

c A nice overall shot showing the back additions for the Car Inspectors house (1 of 1).jpg
A nice overall shot showing the back additions for the Car Inspectors house







.

Re: Cumbres Pass week 3 roof going up

Unread postPosted: Sun Jul 26, 2020 2:03 pm
by John Cole
Bob says those palm nailers really get the job done pounding in those 20D nails.

Re: Cumbres Pass week 3 roof going up

Unread postPosted: Tue Jul 28, 2020 9:03 am
by Sharon Evans
Tom Simco has sent me additional photos from this past week's work.
The roof takes shape (1 of 1).jpg
The roof takes shape

The uprights are going in (1 of 1).jpg
The uprights on the end are going in

The uprights on the end take shape (1 of 1).jpg
The uprights on the end take shape

Nice close up showing the straps used to hold the rafters to the center beam (1 of 1).jpg
Nice close shot showing the straps used to hold the boards in place to the center beam

Looking down from the crown  (1 of 1).jpg
Looking down the roof from the crown

View from the front of the Inspectors house showing the roof boards going in (1 of 1).jpg
View from the front of the Inspectors house showing the roof boards going in




.

Re: Cumbres Pass week 3 roof going up

Unread postPosted: Tue Jul 28, 2020 2:32 pm
by Craig Kumler
Very nice workmenship!