Post Session D - Section House Restoration
Posted: Thu Jul 09, 2015 9:13 am
2015 Work Session "D" was successful in installing the first of three headers and digging three holes for the porch posts. Concrete was poured into the four foot deep holes to a depth of about 18 inches with rebar to establish a foundation for each post footing. Bob Conry is the lead for the Section House restoration and continued work on the facility after the Session. George Trever joined him to setup and pour the three footings. After a week of curing, the work to install the other two headers and all three posts started. Ron Horejsi joined Bob and George to get this key phase of the restoration activity. After many interruptions by rain, the porch roof structure was completed on July 8, 2015.